How to Judge Today's Construction Costs at Japan's Major Home Builders

Published on November 19, 2026

How to Judge Today's Construction Costs at Japan's Major Home Builders

In suburban Kantō, the region around Tokyo, I estimate that a two-story house with 40 tsubo of total floor area would cost about ¥34 million to ¥63 million to build in 2026. The total includes equipment, design, ordinary site work, fees and tax. Land is extra. A tsubo is about 3.31 m², so these houses have about 132 m² across both floors. When comparing prices per tsubo, I’d check which windows, finishes, design services and inspections each builder includes.
I compared seven major Japanese home builders. These companies, often called “house makers” in Japan, sell custom detached houses under their own brands. I used published quotes and company financial reports to estimate what each would charge for its typical finishes and equipment. On that basis, budgets rose by about 20–60% from 2017 to 2026. Some of the increase pays for equipment that changed over the decade, such as better windows or a battery to store solar power.
Would a local builder charge less for a similar two-story house? I estimated the local price in two ways. Under my central assumptions, both methods put the local builder below Sekisui House, Sumitomo Forestry and Sekisui Heim for comparable wood-frame houses. In steel, Sekisui House, Hebel Haus and Sekisui Heim all come in below both local estimates. For the wood-frame designs from Ichijo, Aqura Home and Tama Home, the answer depends on the method.
A major builder offers its own construction system, design services, quality control and inspections. Its system can limit changes to the plan or make a different component cost extra. With a local building company (a kōmuten), you can choose a firm that specializes in the work you want and decide together which materials or details deserve more of the budget. It takes time to check the designer’s experience and how the firm supervises and inspects the work[23].
  1. [23] Hokkaido School Cooperative, "第4回 住宅会社・工務店の選び方 [Part 4: How to choose a housing company or local builder]," 2026.

1. 2026 budgets for a 40-tsubo house

1.1. What the budget covers

I priced a house on an ordinary suburban lot as of November 2, 2026. The budget covers the building and its installed equipment, design, routine site work such as water and drain connections, outdoor work such as parking and fences, and items needed at move-in, including air conditioners, lighting and curtains. It also covers registration, insurance and loan origination fees and interest on a bridge loan. Demolition, ground improvement, special fire protection, furniture, moving and a contingency allowance would add to the budget where needed.
I held floor area and the scope of work constant across builders. I kept the insulation, heating, solar panels and batteries typical of each product, since these are part of what a buyer gets for the price. For example, the Ichijo budget includes whole-house floor heating and a solar-plus-battery package. I left solar panels and batteries out of the Aqura Home and Tama Home budgets because buyers of those base models choose them as options. Each builder’s budget range shows how the total changes with different specifications and different adjustments to the published quotes.

The house and its equipment

The base case has two floors of roughly equal area in Japan’s energy-efficiency climate zone 6. I used the same quantities of outdoor work and the same financing terms across builders. I grouped the building, routine site work and design into a single building subtotal because quotes divide them up differently. It includes built-in systems such as Ichijo’s floor heating and Sekisui Heim’s first-floor air conditioning, Kaiteki Airy, in its steel-frame house. I priced solar panels and batteries separately.

Japan’s insulation grade measures how well the building envelope, including its walls and windows, limits heat transfer. Higher grades require better performance. I assumed grade 5 for Sekisui House and Tama Home’s Dai-Anshin no Ie, grade 6 for Sumitomo Forestry’s Big-Frame wood house and for Hebel Haus and Sekisui Heim in zones 5–7, the equivalent of grade 6 for Aqura Home’s Chō-kūkan no Ie, and grade 7 for Ichijo’s i-smart.

I chose solar and battery configurations for each year using product announcements and published adoption rates. I estimated missing capacities and prices and allowed for uncertainty in the ranges. Ichijo’s 2026 figure is a package price. The Sekisui House steel budget also includes a home energy management system (HEMS), which monitors and manages household electricity use.

Table 1. Solar and battery assumptions in 2017 and 2026Two stories, 40 tsubo in suburban Kantō. The budget is the owner’s installed cost in 2026. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
Builder and frame2017 configuration2026 configuration2026 equipment budget
Sekisui House, wood4 kW solar, no battery4 kW solar, no battery1.5(0.038 per tsubo)
Sumitomo Forestry, wood4.3 kW solar, no battery5 kW solar, no battery1.6(0.040 per tsubo)
Sekisui Heim, wood5 kW solar, no battery7 kW solar, 13.2 kWh battery4.0(0.100 per tsubo)
Ichijo, woodAbout 10–12 kW solar, no batteryAbout 13.5 kW solar, about 7 kWh battery2.9(0.073 per tsubo)
Aqura Home, woodNo solar panels or batteryNo solar panels or battery0.0(0.000 per tsubo)
Tama Home, woodNo solar panels or batteryNo solar panels or battery0.0(0.000 per tsubo)
Sekisui House, steel5 kW solar and HEMS, no battery5 kW solar and HEMS, no battery1.6(0.040 per tsubo)
Hebel Haus, steelNo solar panels or battery5 kW solar, no battery1.6(0.040 per tsubo)
Sekisui Heim, steel5.5 kW solar, no battery7 kW solar, 13.2 kWh battery4.0(0.100 per tsubo)

For Sekisui Heim, I kept the 13.2 kWh battery used in the earlier material for comparability. At the research date the company offered 5.7, 11.4 and 17.1 kWh. The steel-frame budget also retains Kaiteki Airy and makes no allowance for switching to a newer system such as AirLax. All equipment budgets assume the owner buys the system and pays for installation. Subsidies, savings on electricity bills and revenue from selling electricity fall outside these upfront figures, as do third-party ownership plans with no upfront charge.

How I adjusted the quotes

For each example I recorded the product, structure, date the price was set, floor area, construction area, discount, tax and work included. Construction area can include balconies that the total floor area excludes. I scaled the building subtotal to 40 tsubo of total floor area, then priced outdoor work and financing separately. I used the date the price was set even when the figures appeared online later.

Two owners’ figures illustrate the adjustment. For a wood-frame Sekisui House I used an October 2025 financing plan for about 40.7 tsubo. For Sumitomo Forestry I used a July 2026 estimate for a one-story house of about 25.5 tsubo. I removed lighting and other items counted separately or outside the budget, then adjusted for size, date and, for Sumitomo Forestry, the second floor. The resulting building subtotals were about ¥55.4 million and ¥51.9 million. After comparing them with other sources, I budgeted ¥56 million and ¥53 million, respectively[6, 4].

To adjust for size, I divided 40 tsubo by the quoted floor area in tsubo, raised that ratio to the power of 0.85 and multiplied the relevant costs by the result. I allowed 3.1% for the change in date for Sekisui House and 0.9% for Sumitomo Forestry. For the latter I also divided by 1.08 to convert a one-story design into a two-story one. I could check the owners’ transcriptions but had no access to the original contracts. The coefficients are assumptions, and extrapolating from the small one-story house is a particularly large source of uncertainty.

Outdoor work, fees and financing

I allowed ¥2.5 million for outdoor work, including two parking spaces, and ¥1.2 million for air conditioners, lighting and curtains. Ichijo’s floor heating still leaves the house needing summer cooling. For Sekisui Heim steel, the first-floor system already covers part of that need, so I deducted ¥0.3 million from the air-conditioning allowance and budgeted ¥0.9 million for move-in items.

I added ¥350,000 for registration, ¥250,000 for the first insurance premium, ¥30,000 for stamp duty and ¥200,000 for water connection and related charges. I assumed the buyer borrows 80% of the tax-inclusive cost of construction and equipment. I assumed an origination fee of 2% of the loan, plus consumption tax on the fee. Bridge interest runs at 2% a year for an effective three months, accounting for how much the buyer draws and how long it is outstanding.

I applied consumption tax to taxable work and to the origination fee. I allowed ¥50,000 in statutory fees within design and permitting for 2017–2024 and ¥100,000 from 2025. I carried those fees, registration, insurance and interest at the amounts payable. When I reassigned an item such as solar panels, I deducted it from the original category.

Price evidence and rounding

I checked the resulting budgets against prices in investor reports, taking account of floor area, product mix and what the reported price covers. Sekisui House and Sekisui Heim combine wood and steel in their published averages. Sekisui Heim’s nationwide figures and its figures for consolidated sales companies cover different groups. Sumitomo Forestry reports orders and deliveries separately[24, 25, 26].

I counted repeated reports of a single quote once. I reproduced the calculations in the underlying research but did not consult every original source myself. The central figure is a budget for the specified house. The endpoints show how far it moves when the specifications or price adjustments change.

In the budget tables I round whole-house amounts to the nearest ¥0.1 million. I calculated amounts per tsubo, differences and percentages before rounding. The budget downloads include Japanese labels and give house costs in units of ¥10,000, so a total of 100 means ¥1 million.

  1. [6] Sekisui House, "戸建住宅・注文住宅 [Detached and custom-built houses]," 2026. The wood budget draws on an owner’s October 2025 financing plan. Other price evidence includes a steel-frame quote and an owner’s construction costs. Sekisui House describes its insulation system.
  2. [4] Sumitomo Forestry, "木造注文住宅・戸建の住友林業 [Sumitomo Forestry: custom-built wooden and detached houses]," 2026. The wood budget draws on an owner’s July 2026 estimate for a one-story house of 25.5 tsubo. Other owners published a 2017 quote and 2024 costs. The company reports equipment uptake in its 2019 sustainability report and more recent environmental reporting.
  3. [5] Asahi Kasei Homes, "注文住宅・戸建住宅 [Custom-built and detached houses]," 2026. Owners report prices for the building itself and a contract total. The company describes its standard solar and insulation specifications.
  4. [7] Sekisui Chemical, "セキスイハイム(ハウスメーカー)|注文住宅・分譲住宅 [Sekisui Heim (house maker): custom-built and built-for-sale houses]," 2026. For wood, the evidence includes a 2022 quote and an anonymous report of a 2025 contract without a verified breakdown. For steel, it includes a 2025 contract example.
  5. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. Price evidence includes a 2018 quote, a 2023 sales comparison sheet and a transcription of 2026 prices. Ichijo describes its solar and battery system.
  6. [8] AQ Group, "AQ Group アキュラホーム [AQ Group Aqura Home]," 2026. Owners published an itemized quote and a final 2023 quote.
  7. [9] Tama Home, "家を建てるならタマホーム株式会社 [Tama Home for building your house]," 2026. For prices, tax and discounts, see a 2024 quote and an owner’s account of the discount terms.
  8. [24] Sekisui House, "2026年度第2四半期 Financial Factbook [Financial Factbook for the second quarter of FY2026]," 2026. Average prices and floor areas for custom homes, combining wood and steel frames.
  9. [25] Sekisui Chemical, "2025年度決算および2026年度経営計画説明会 [Briefing on FY2025 results and the FY2026 management plan]," 2026. The first-half fiscal 2026 report gives current and restated prior-year figures for consolidated sales companies. The older nationwide series includes other sales companies.
  10. [26] Sumitomo Forestry, "2026年12月期第2四半期 Financial Factbook [Financial Factbook for the second quarter of the fiscal year ending December 2026]," 2026.

1.2. Two stories or three, in wood or steel

For a two-story house, the wood-frame budgets run from about ¥34 million at Tama Home to ¥63 million at Sekisui House (¥0.86–1.58 million per tsubo). The steel-frame budgets run from about ¥51 million at Sekisui Heim to ¥63 million at Sekisui House (¥1.28–1.59 million per tsubo). The two Sekisui House totals are close in part because I used the same subtotal for the building, routine site work and design. The available quotes did not isolate the cost of changing frames on the same plan. Figure 1 shows how far each budget moves under the low and high assumptions.
Putting the same floor area on three stories gives about ¥40–68 million for wood and ¥58–71 million for steel. I had few direct three-story quotes, so I estimated the added structural work, site work and design, then allowed for the smaller roof area available for solar panels.
For 40 tsubo, two-story wood budgets range from about ¥34 million at Tama Home to ¥63 million at Sekisui House. Steel ranges from ¥51 million at Sekisui Heim to ¥63 million at Sekisui House. Three-story budgets are higher for each builder and frame shown. Many builders’ ranges overlap.
Figure 1: Estimated 2026 budgets by builder, frame and number of stories For 40 tsubo in suburban Kantō, including tax and excluding land. Each point marks the budget for the builder’s typical specifications. The line spans the low and high budgets. Green marks wood, blue steel. Circles show two stories and triangles show three. Read the total in millions of yen below or the price per tsubo in millions of yen above. The three-story estimates use assumed additions to the two-story budgets. There is no three-story wood case for Sekisui Heim.

The building subtotal covers the structure, routine site work and design. The total also includes the solar and battery equipment shown separately, outdoor work, move-in items and fees. The low and high budgets vary both the specification and the adjustments to the source prices.

Table 2. Two-story wood-frame budgets2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
BuilderBuilding, site work and designSolar and battery equipmentTotal budgetLow–high budget
Sekisui House56.0(1.400 per tsubo)1.5(0.038 per tsubo)63.4(1.584 per tsubo)56.0–77.0(1.400–1.926 per tsubo)
Sumitomo Forestry53.0(1.325 per tsubo)1.6(0.040 per tsubo)60.4(1.510 per tsubo)52.0–71.1(1.300–1.778 per tsubo)
Sekisui Heim40.0(1.000 per tsubo)4.0(0.100 per tsubo)49.6(1.239 per tsubo)41.7–59.7(1.042–1.492 per tsubo)
Ichijo38.0(0.950 per tsubo)2.9(0.073 per tsubo)46.4(1.160 per tsubo)40.5–54.1(1.012–1.351 per tsubo)
Aqura Home36.0(0.900 per tsubo)0.0(0.000 per tsubo)41.4(1.035 per tsubo)35.4–49.5(0.884–1.237 per tsubo)
Tama Home29.0(0.725 per tsubo)0.0(0.000 per tsubo)34.2(0.856 per tsubo)29.2–40.3(0.731–1.007 per tsubo)

For Hebel Haus, I moved solar panels out of the original building price and into the equipment column. Sekisui Heim’s built-in first-floor air conditioning stays in the building subtotal. The two Sekisui House budgets differ in their solar equipment and the associated fees.

Table 3. Two-story steel-frame budgets2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
BuilderBuilding, site work and designSolar and battery equipmentTotal budgetLow–high budget
Sekisui House56.0(1.400 per tsubo)1.6(0.040 per tsubo)63.5(1.586 per tsubo)55.1–76.2(1.377–1.906 per tsubo)
Hebel Haus54.0(1.350 per tsubo)1.6(0.040 per tsubo)61.4(1.535 per tsubo)52.0–74.2(1.300–1.855 per tsubo)
Sekisui Heim42.0(1.050 per tsubo)4.0(0.100 per tsubo)51.3(1.282 per tsubo)43.5–62.4(1.087–1.559 per tsubo)

For three stories, I added ¥4.5–6.5 million for the building itself, ¥0.4 million for site work and ¥0.5 million for design, then recalculated loan costs. Stairs, piping and structural requirements change even at the same total floor area. Sekisui House, for example, uses different structural systems for two- and three-story steel houses[6].

With floors of roughly equal area, the three-story roof has two-thirds the area of the two-story roof. I scaled solar capacity accordingly and kept battery capacity fixed. Where there are panels, I retained a fixed installation allowance of ¥150,000 and took two-thirds of the remaining solar cost. Splitting a package price introduces uncertainty. An actual three-story quote needs the roof layout, openings, insulation and fire requirements for the particular site.

Table 4. Three-story budgets based on assumed construction premiums2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
Builder and frameBuilding, site work and designSolar and battery equipmentTotal budget
Sekisui House, wood61.4(1.535 per tsubo)1.1(0.026 per tsubo)68.4(1.710 per tsubo)
Sumitomo Forestry, wood60.4(1.510 per tsubo)1.1(0.028 per tsubo)67.5(1.686 per tsubo)
Ichijo, wood44.4(1.110 per tsubo)2.3(0.057 per tsubo)52.3(1.308 per tsubo)
Aqura Home, wood41.9(1.048 per tsubo)0.0(0.000 per tsubo)47.4(1.185 per tsubo)
Tama Home, wood34.4(0.860 per tsubo)0.0(0.000 per tsubo)39.8(0.994 per tsubo)
Sekisui House, steel63.4(1.585 per tsubo)1.1(0.028 per tsubo)70.5(1.763 per tsubo)
Hebel Haus, steel60.1(1.503 per tsubo)1.1(0.028 per tsubo)67.1(1.679 per tsubo)
Sekisui Heim, steel49.4(1.235 per tsubo)3.3(0.083 per tsubo)58.2(1.454 per tsubo)

2. How budgets changed from 2017 to 2026

2.1. What the construction cost index measures

The materials and labor that go into a house became more expensive over this period. With the 2017 average set to 100, Japan’s construction cost deflator averaged 133 for wood-frame houses and 135 for steel-frame houses in January–August 2026[1]. One example was the 2021 lumber shortage. Rising US demand and disruptions to ocean shipping cut the supply of imported lumber in Japan. Buyers turned to domestic lumber, pushing up its price as well[2].
A builder’s selling price also reflects what comes with the house and when the company passes higher costs on to buyers. I therefore used each company’s own price evidence to estimate buyers’ budgets. The national index gives those changes a point of comparison.
Both cost indices start at 100 in 2017. Wood rises to about 123 in 2022, dips to 121 in 2023 and reaches 133 in January–August 2026. Steel rises throughout and reaches 135 in the same eight-month period.
Figure 2: Japanese housing construction cost indices, 2017–2026 Japan’s Ministry of Land, Infrastructure, Transport and Tourism (MLIT) tracks construction input costs excluding changes in consumption tax. The lines show averages relative to 2017 for wood (solid green) and steel (dotted blue). The last point covers January–August 2026. Earlier points cover full calendar years[1].
I took wood-frame housing from column F and steel-frame housing from column J of MLIT’s monthly spreadsheet. For each series, I divided the mean of the available months in each year by the 2017 mean and multiplied by 100. The annual index data (CSV) include both the original and rebased values.

2.2. Budgets with each year’s typical specifications

From 2017 to 2026, the estimated budget for a 40-tsubo, two-story house rose by about 20% for Ichijo and about 35–60% for the other eight combinations of builder and frame. These figures include changes in the house as well as in prices. I used quotes, contract examples, product announcements and financial reports to estimate the combined cost of the building, routine site work and design in 2017, 2020, 2023 and 2026. Between those years I assumed a constant annual growth rate for that subtotal. The curves therefore cannot date an individual price increase.
All nine estimated budgets rise. Tama Home goes from about ¥24 million in 2017 to ¥34 million in 2026. Ichijo rises least in percentage terms, from about ¥39 million to ¥46 million. Hebel Haus rises most, from about ¥38 million to ¥61 million.
Figure 3: Budgets for two-story houses with each year’s typical specifications Tax-inclusive budgets for 40 tsubo in suburban Kantō, excluding land. Each budget includes that year’s typical equipment and applicable tax. I estimated the building, site work and design costs in 2017, 2020, 2023 and 2026. Between those dates I assumed constant annual growth in that subtotal, so the slopes tell us little about when a builder raised its prices. Each color identifies a company. Solid lines show wood and dotted lines show steel. The left axis gives millions of yen for the whole house and the right gives millions of yen per tsubo.

Prices between the four base years

I used the 2026 building subtotals from Section 1 and set the three earlier subtotals from published quotes and related evidence. Between successive base years, I interpolated each builder’s subtotal at the annual compound rate that connects the two values. Annual changes in company-reported average prices also reflect house sizes, product mix and the reporting date. The alternative calculations (JSON) include a version that uses those reported growth rates.

For companies that sold both wood and steel houses, few sources priced the two frames on the same terms. I assumed equal building subtotals for Sekisui House wood and steel and estimated the split between building, site work and design. I removed ground improvement, furniture, moving and contingencies from the original budgets where present, and recalculated financing on common terms.

To estimate outdoor work in an earlier year, I took its pre-tax cost in each company’s source and divided by its 2026 counterpart. I averaged the ratios for wood and steel within a company, then multiplied the median of the company ratios by the common 2026 allowance. Each company thus carries the same weight, even when it contributes two series. I repeated the calculation separately for move-in items.

Changes in equipment

I included options when adoption figures or quotes indicated that they were typical. For years before Japan introduced insulation grades 5–7, I compared the actual insulation and windows. Ichijo’s i-smart already had highly insulating windows and whole-house floor heating early in the period. Its pre-tax price per tsubo for the building itself also rose more slowly in the available quotes than those of the other builders[3].

A 2017 Sumitomo Forestry quote already included solar panels[4]. I assumed 4.3 kW from 2017 through 2023 and 5 kW from 2024. Scaling a ¥1.9 million allowance for 5 kW to 4.3 kW gives about ¥1.6 million for 2017. The 4.3 kW is my assumed capacity.

Sekisui Heim reported batteries in 21% of its new detached houses in fiscal 2017, 55% in fiscal 2019 and 83% in fiscal 2022[25]. Drawing on those figures and product updates, I moved from no battery to 8, 12 and eventually 13.2 kWh. I estimated costs for years without capacity-specific prices. When comparing the company’s 2026 first-half price figures with the previous year, I used the restated prior-year figures covering the same sales companies.

For Hebel Haus, I included solar panels from May 2024, when they became standard. I estimated their share of the building price because the quote did not price them separately. The budget also reflects the 2025 move to insulation grade 6[5].

Consumption tax and financing

Japan raised consumption tax from 8% to 10% in October 2019. For the comparison I used 8% in 2017–2019, assuming a contract eligible for transitional treatment in 2019, and 10% from 2020[27]. If a source used 10% or an approximate 8.5%, I backed out that tax first. The tax comparison (JSON) also prices 2019 at 10%.

For each year I recalculated the loan against the tax-inclusive construction and equipment costs, then applied that year’s tax to the origination fee. Registration, insurance, statutory fees and bridge interest enter at the amounts payable. Contingency and savings for future repairs are outside the construction budget and loan principal.

Table 5. Change in the typical two-story budget by builderTwo stories, 40 tsubo in suburban Kantō, with each year’s typical equipment. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
Builder and frame2017 budget2026 budgetIncrease from 2017
Sekisui House, wood41.2(1.030 per tsubo)63.4(1.584 per tsubo)53.7%
Sumitomo Forestry, wood40.1(1.004 per tsubo)60.4(1.510 per tsubo)50.4%
Sekisui Heim, wood36.0(0.899 per tsubo)49.6(1.239 per tsubo)37.9%
Ichijo, wood38.6(0.964 per tsubo)46.4(1.160 per tsubo)20.3%
Aqura Home, wood26.9(0.672 per tsubo)41.4(1.035 per tsubo)53.9%
Tama Home, wood24.1(0.603 per tsubo)34.2(0.856 per tsubo)41.8%
Sekisui House, steel41.4(1.035 per tsubo)63.5(1.586 per tsubo)53.2%
Hebel Haus, steel38.5(0.962 per tsubo)61.4(1.535 per tsubo)59.6%
Sekisui Heim, steel38.1(0.952 per tsubo)51.3(1.282 per tsubo)34.7%
Table 6. Annual budgets with each year’s typical specificationsTwo stories, 40 tsubo in suburban Kantō, with each year’s typical equipment. Amounts in millions of yen, including tax and excluding land. Building subtotals between 2017, 2020, 2023 and 2026 are interpolated.
Builder and frame2017201820192020202120222023202420252026
Sekisui House, wood41.242.343.445.548.050.953.856.960.163.4
Sumitomo Forestry, wood40.141.242.344.346.949.752.755.357.860.4
Sekisui Heim, wood36.036.538.339.541.242.944.946.047.949.6
Ichijo, wood38.639.340.041.442.243.244.245.145.846.4
Aqura Home, wood26.927.528.129.331.634.136.638.239.841.4
Tama Home, wood24.124.725.426.527.929.531.032.133.234.2
Sekisui House, steel41.442.543.645.648.251.053.957.060.263.5
Hebel Haus, steel38.539.440.542.345.248.551.856.058.761.4
Sekisui Heim, steel38.138.640.541.743.545.447.648.549.951.3

The annual budgets (CSV) give the components, tax rates, equipment capacities and specifications. For Tama Home I used the quote after its ¥1 million discount and kept design, supervision, permits and site management in the subtotal. For Aqura Home, the design line and subtotal disagree on tax, and the solar cost is unclear. The budget range allows for those uncertainties and for the date of the quote[9, 8]. The wood-frame Sekisui Heim figures draw in part on a specially discounted quote and an anonymous owner’s report. Small differences from its steel-frame price are sensitive to those sources.

  1. [4] Sumitomo Forestry, "木造注文住宅・戸建の住友林業 [Sumitomo Forestry: custom-built wooden and detached houses]," 2026. The 2017 quote includes solar panels. The comparison assumes 4.3 kW.
  2. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. Compare an original 2018 quote with a transcription of 2026 prices.
  3. [25] Sekisui Chemical, "2025年度決算および2026年度経営計画説明会 [Briefing on FY2025 results and the FY2026 management plan]," 2026. Sekisui Chemical reports battery adoption in its fiscal 2018, fiscal 2020 and fiscal 2022 results. The first-half fiscal 2026 results explain the change in sales companies covered.
  4. [5] Asahi Kasei Homes, "注文住宅・戸建住宅 [Custom-built and detached houses]," 2026. The April 2025 announcement dates the changes in standard equipment.
  5. [9] Tama Home, "家を建てるならタマホーム株式会社 [Tama Home for building your house]," 2026. An image of the 2024 quote shows the discount and tax treatment.
  6. [8] AQ Group, "AQ Group アキュラホーム [AQ Group Aqura Home]," 2026. The transcribed quote for 37.57 tsubo leaves some uncertainty about the price date and tax on the design fee.
  7. [27] National Tax Agency, Consumption Tax Office, "消費税率等に関する経過措置の取扱いQ&A(基本的な考え方編) [Q&A on transitional measures for the consumption tax rate (basic concepts)]," 2018. Transitional provisions governing which construction contracts could still use the 8% rate.
Ichijo starts from a different place than a builder that added better windows or whole-house heating later. Its i-smart line already included both in the early years[3]. I also allowed almost the same amount for its smaller 2017 solar array as for its larger 2026 array with a battery. That assumption helps explain the relatively small increase in the total.
For Sumitomo Forestry, the building, site work and design accounted for about 90% of the budget increase. The company says it raised quoted prices in stages from 2021. Even after lumber prices eased, other materials and energy remained expensive, and labor was still scarce[4]. At Hebel Haus, the building subtotal accounted for about 85% of the increase, including the upgrade to insulation grade 6. The total also reflects the solar panels that became standard in 2024[5].
The 2017 Sumitomo Forestry budget was about ¥1.6 million higher than Ichijo’s. To see how the equipment included in each price affects that comparison, remove the panels and their financing costs from both houses. Ichijo’s larger solar array accounted for more of its budget, so the gap widens to about ¥2.8 million.

The 2017 Ichijo budget was ¥38.6 million, including about ¥2.8 million for solar. The Sumitomo Forestry budget was ¥40.1 million, including about ¥1.6 million for solar. With solar removed and loan fees and bridge interest recalculated, the respective totals are ¥35.7 million and ¥38.5 million. Each house keeps its original insulation, structure and finishes.

Table 7. 2017 budgets with and without solar and storageTwo stories, 40 tsubo in suburban Kantō. Each builder’s 2017 specifications. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo. The budget without the equipment also removes its financing costs.
Builder and frameBuilding, site work and designSolar and battery equipmentTotal budgetTotal without solar and storageLow–high budget
Sekisui House, wood35.7(0.892 per tsubo)1.6(0.040 per tsubo)41.2(1.030 per tsubo)39.6(0.989 per tsubo)35.8–47.8(0.894–1.194 per tsubo)
Sumitomo Forestry, wood34.6(0.865 per tsubo)1.6(0.041 per tsubo)40.1(1.004 per tsubo)38.5(0.962 per tsubo)34.7–46.9(0.867–1.172 per tsubo)
Sekisui Heim, wood30.3(0.757 per tsubo)1.9(0.046 per tsubo)36.0(0.899 per tsubo)34.1(0.852 per tsubo)31.5–41.6(0.786–1.039 per tsubo)
Ichijo, wood31.9(0.798 per tsubo)2.8(0.070 per tsubo)38.6(0.964 per tsubo)35.7(0.893 per tsubo)34.8–43.2(0.870–1.081 per tsubo)
Aqura Home, wood23.3(0.582 per tsubo)0.0(0.000 per tsubo)26.9(0.672 per tsubo)26.9(0.672 per tsubo)22.4–31.9(0.560–0.798 per tsubo)
Tama Home, wood20.6(0.514 per tsubo)0.0(0.000 per tsubo)24.1(0.603 per tsubo)24.1(0.603 per tsubo)21.3–27.5(0.533–0.688 per tsubo)
Sekisui House, steel35.7(0.892 per tsubo)1.8(0.045 per tsubo)41.4(1.035 per tsubo)39.6(0.989 per tsubo)35.9–48.0(0.898–1.200 per tsubo)
Hebel Haus, steel34.6(0.865 per tsubo)0.0(0.000 per tsubo)38.5(0.962 per tsubo)38.5(0.962 per tsubo)33.4–44.6(0.836–1.115 per tsubo)
Sekisui Heim, steel32.5(0.811 per tsubo)2.0(0.050 per tsubo)38.1(0.952 per tsubo)36.0(0.901 per tsubo)32.5–43.7(0.812–1.092 per tsubo)

Near the 2017 base year, an Ichijo quote gave a pre-tax price of about ¥646,000 per tsubo for the building, using about 31 tsubo of construction area. A Sumitomo Forestry quote gave a discounted ¥22.08 million for the building and design on about 30 tsubo of construction area[3, 4]. I adjusted for area, options, solar and discounts and checked the results against the companies’ reports.

For Sekisui House, Hebel Haus and Sekisui Heim, some reports omit the tax treatment, use the delivery year for an earlier contract, or combine wood and steel. The evidence cannot resolve close rankings[6, 5, 25]. Aqura Home’s limited-time product and Tama Home’s company reports support lower budgets, but their special equipment and mix of lower-priced products limit how closely they match a 40-tsubo house[8, 9].

Table 8. Change in two-story budgets by cost category, 2017–2026Two stories, 40 tsubo in suburban Kantō, with each year’s typical equipment. Amounts in millions of yen, including tax and excluding land. Changes include the higher tax rate. Other costs include outdoor work, move-in items, fees and the rounding needed to sum to the total.
Builder and frameChange in building, site work and designChange in solar and storageChange in other costsChange in total
Sekisui House, wood20.3−0.11.922.1
Sumitomo Forestry, wood18.40.01.820.2
Sekisui Heim, wood9.72.21.713.6
Ichijo, wood6.10.11.67.8
Aqura Home, wood12.70.01.814.5
Tama Home, wood8.40.01.710.1
Sekisui House, steel20.3−0.21.922.0
Hebel Haus, steel19.41.61.922.9
Sekisui Heim, steel9.62.01.613.2

Table 8 shows where the increase appears in the buyer’s budget. The building subtotal combines materials, labor and the builder’s margin, so separating their contributions would require a more detailed breakdown.

For Ichijo I budgeted ¥2.8 million for solar alone in 2017 and ¥2.9 million for solar and a battery in 2026. The extra ¥0.1 million follows from those equipment assumptions. The quotes do not isolate the savings from in-house production. The year an equipment change enters the budget also affects the curve. Sumitomo Forestry’s earnings briefing describes a further lag between revising a quote and recognizing the sale[4].

The historical cost breakdown (JSON) gives unrounded changes, budgets without solar and storage, and the evidence behind each choice.

  1. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. See the owner’s 2018 contract figures and Ichijo’s description of its earlier i-series specifications.
  2. [4] Sumitomo Forestry, "木造注文住宅・戸建の住友林業 [Sumitomo Forestry: custom-built wooden and detached houses]," 2026. Prices come from a discounted 2017 quote, Sumitomo Forestry’s announcement for The Forest BF and the company’s Factbook. Its second-quarter 2023 earnings Q&A discusses the lag between price changes and reported sales.
  3. [6] Sekisui House, "戸建住宅・注文住宅 [Detached and custom-built houses]," 2026. The self-reported 2016 wood quote for 37.13 tsubo leaves the tax treatment unclear. The steel example gives final costs for a 41-tsubo IS ROY+E and the 2017 contract with its 2018 changes. I adjusted for outdoor work, demolition and added features.
  4. [5] Asahi Kasei Homes, "注文住宅・戸建住宅 [Custom-built and detached houses]," 2026. In an account of 2017 negotiations, the price changed along with the floor area, discount and plumbing work.
  5. [25] Sekisui Chemical, "2025年度決算および2026年度経営計画説明会 [Briefing on FY2025 results and the FY2026 management plan]," 2026. Individual reports describe a 33-tsubo wood house without solar in 2017 and a 2016 steel contract delivered in 2017. The fiscal 2018 company results combine wood and steel.
  6. [8] AQ Group, "AQ Group アキュラホーム [AQ Group Aqura Home]," 2026. In its 2017 announcement, Aqura offered a limited-time 35.57-tsubo house with 10.73 kW of solar from ¥19.99 million including tax.
  7. [9] Tama Home, "家を建てるならタマホーム株式会社 [Tama Home for building your house]," 2026. The securities report for the year ended May 2017 gives company-wide figures that include regional and lower-priced products.

2.3. What comparable performance would have cost

What would the 2017 house have cost with the insulation, windows and solar equipment the same builder offered in 2026? I used each design’s own 2026 specification as the target. For Ichijo that meant pricing a large solar array and a battery in every year. For Tama Home’s base model it meant leaving both out. I used each year’s prices and consumption tax rate, leaving out changes in warranty coverage and improvements I couldn’t price. Across the nine two-story designs, the resulting increases from 2017 to 2026 ranged from about 14% to 54%.
Pricing earlier houses closer to each builder’s 2026 specifications reduces the estimated increase to about 14% for Ichijo, 19% for Sekisui Heim steel and 46% for Sumitomo Forestry. Sekisui House wood still rises about 54%. All lines end at the same 2026 values as in Figure 3.
Figure 4: Two-story budgets at specifications comparable to 2026 Estimated tax-inclusive budgets for 40 tsubo in suburban Kantō, excluding land. The allowances for upgrades and equipment cover insulation, windows, air conditioning, finishes and solar and battery capacity where the cost difference could be estimated. The scales match Figure 3, with millions of yen per house at left and per tsubo at right. Each color identifies a builder. Solid lines show wood and dotted lines show steel.

Pricing upgrades in an earlier year

For each builder I started with the building subtotal in Figure 3 and added an allowance for the upgrades needed in that year. Table 9 expresses the allowances at tax-inclusive 2026 prices. To price an upgrade in an earlier year, I first converted the allowance to a pre-tax amount. I scaled it by that year’s building subtotal divided by the 2026 subtotal, both before tax, then applied the earlier year’s tax rate.

Table 9. Assumed cost of upgrading the earlier building specificationTwo stories, 40 tsubo in suburban Kantō. Each allowance is in millions of yen at tax-inclusive 2026 prices. Solar and batteries are priced separately.
Builder and frameYear and allowance for insulation, windows and other upgrades
Sekisui House, wood2017–2026: 0.0
Sumitomo Forestry, wood2017–2020: 1.5
2021–2023: 1.0
2024: 0.5
2025–2026: 0.0
Sekisui Heim, wood2017–2023: 1.5
2024–2026: 0.0
Ichijo, wood2017–2025: 0.0 (alternative allowance 0–0.8)
2026: 0.0
Aqura Home, wood2017–2021: 2.5
2022–2024: 1.0
2025–2026: 0.0
Tama Home, wood2017–2021: 1.0
2022–2026: 0.0
Sekisui House, steel2017–2026: 0.0
Hebel Haus, steel2017–2024: 1.5
2025–2026: 0.0
Sekisui Heim, steel2017–2023: 1.5
2024–2026: 0.0

For Ichijo I kept the well-insulated, floor-heated i-smart as the baseline. A 2024 quote offered grade 7 at no extra charge during a promotion. It provides too little evidence for a single surcharge across all sites and years before grade 7 became standard in 2026[3]. I used a zero allowance and tested additions up to ¥0.8 million at 2026 prices.

For Sekisui House I assumed that walls, windows and the rest of the building envelope continued to meet Japan’s net zero energy house (ZEH) insulation standard. I used a zero allowance for individual upgrades whose costs I could not establish. I also left out differences in detailing, component models and minor equipment revisions where their cost was unknown.

Pricing the same solar and battery capacity

I held solar output and battery capacity at each builder’s 2026 levels. For each earlier year I split the equipment budget into solar and battery costs, scaled each to the target capacity and replaced the original equipment allowance. The division of Ichijo’s package price between panels and battery is an estimate.

For a year with no battery in the typical specification, I worked backward from the first year with a battery allowance (2020 for Ichijo and 2019 for Sekisui Heim). Surveys of residential systems in subsidy programs gave equipment costs of ¥188,000, ¥173,000 and ¥140,000 per kWh in fiscal 2017, 2018 and 2019[28]. I used the ratios between those costs and assumed the 2020 rate equaled 2019. Applying equipment-only ratios to installed systems, and scaling costs in proportion to capacity, are approximations. The surveys cover different groups of systems.

I recalculated the origination fee and bridge interest on the new construction and equipment total. The tax rates, outdoor work, move-in items and other charges follow Figure 3. For Ichijo, about ¥6.1 million more for the building subtotal and ¥1.6 million more for other costs are partly offset by a fall from ¥4.8 million to ¥2.9 million for the same solar and battery capacity. That leaves an increase of about ¥5.8 million.

Table 10. Change in budget with specifications closer to 2026Two stories, 40 tsubo in suburban Kantō. Each house is priced as close as possible to its own builder’s 2026 performance and equipment. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo.
Builder and frameAdjusted 2017 budget2026 budgetIncrease from adjusted 2017 budget
Sekisui House, wood41.2(1.030 per tsubo)63.4(1.584 per tsubo)53.7%
Sumitomo Forestry, wood41.4(1.035 per tsubo)60.4(1.510 per tsubo)45.8%
Sekisui Heim, wood40.5(1.012 per tsubo)49.6(1.239 per tsubo)22.4%
Ichijo, wood40.6(1.016 per tsubo)46.4(1.160 per tsubo)14.2%
Aqura Home, wood28.5(0.714 per tsubo)41.4(1.035 per tsubo)45.0%
Tama Home, wood24.9(0.622 per tsubo)34.2(0.856 per tsubo)37.7%
Sekisui House, steel41.4(1.035 per tsubo)63.5(1.586 per tsubo)53.2%
Hebel Haus, steel41.4(1.035 per tsubo)61.4(1.535 per tsubo)48.3%
Sekisui Heim, steel43.0(1.075 per tsubo)51.3(1.282 per tsubo)19.3%

The adjusted annual budgets (CSV) include all nine series and the component costs, capacities and adjustments behind them. The alternative totals vary the building upgrade allowance from zero to twice its central value (¥0–0.8 million for Ichijo through 2025) and the equipment adjustment from 75% to 125% of its central value.

  1. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. The November 2024 quote covers a promotion for one single-story house with 19.16 tsubo of construction area.
  2. [28] Mitsubishi Research Institute, "2024年度 定置用蓄電システム普及拡大検討会の結果とりまとめ [FY2024 report of the study group on expanding the use of stationary battery systems]," Ministry of Economy, Trade and Industry, 2025. Earlier ministry meeting papers give equipment prices for fiscal 2017 and 2018 and survey results for fiscal 2019.
For Ichijo, I estimate that the same solar and battery capacity would have cost about ¥4.8 million in 2017 and ¥2.9 million in 2026. That drop partly offsets higher costs for the building, site work and design. The total budget rises by about 14%, compared with 20% using each year’s typical equipment. The result depends in part on my estimate of the 2017 battery price.
For a wood-frame Sekisui House, both comparisons give a rise of about 54%. I assumed 4 kW of solar in both years and could assign no separate cost to changes in the building itself.
When you use an old price per tsubo to assess a current quote, start with the contract date and the equipment it bought. A larger solar array, better windows or a new battery may account for part of the difference. Getting those items priced separately shows which costs you could change by choosing a different specification.

3. What a local builder might charge for a similar house

3.1. Two ways to estimate the price

A lower quote from a local builder means little if it leaves out the windows, woodwork or heating you wanted. I kept the site, floor area and budget coverage from Section 1 and assumed a local builder capable of the design and construction. I priced commercially available materials and methods that could approximate each house. Proprietary components, construction details and warranty service may still differ.
For the first estimate (A), I started with a local builder’s base price and added the upgrades a local builder could supply. Take the two-story wood-frame Sekisui House. Starting at ¥30.5 million, I allowed extra for the structure and large windows, ceramic cladding, interior finishes, design and inspection. With solar panels, outdoor work, move-in items and fees, the local estimate comes to ¥47.0 million.

The base house and the cost of changing it

For 40 tsubo on two stories in suburban Kantō, I used 2026 tax-inclusive base prices of ¥30.5 million for wood at insulation grade 5, ¥34 million for wood at grade 6 and ¥50 million for individually designed steel at grade 5. The base includes ordinary design, permits, structural review, construction management, on-site water and drainage work, finishes and equipment. For wood, I assumed seismic grade 3, the highest of Japan’s three grades for earthquake resistance. For steel, the base includes structural design and upper floors made of autoclaved lightweight concrete (ALC). A third story adds a central allowance of ¥3.5 million for wood or ¥4 million for steel.

Some local builders quote a price per tsubo of construction area, which can include balconies, and some charge separately for design or site work that others include[29, 30]. The published prices of architectural firms for steel-frame houses also cover different scopes[31, 32]. I used these prices to set the base allowances after checking what the area and price included.

For the wood-frame Sekisui House example, I added ¥2.8 million for the structure and windows, about ¥2.7 million for exterior cladding, ¥3 million for interior finishes and fixtures, and ¥1.4 million for extra design and inspection. The ¥47.0 million total also includes 4 kW of solar and the other costs of moving into the house. The major builder’s comparable budget is ¥63.4 million.

Exterior walls

I used the same quantities and rates for the same work across builders. For square floors of roughly equal size, a floor-to-floor height of 3 m and openings covering 15% of the wall area, about 166 m² of exterior wall needs cladding on two stories, or 203 m² on three. Scaffolding, the weather barrier and the ventilation cavity are already in the base price. Each upgrade adds only the difference from standard siding.

Table 11. Local builder’s installed cladding costs2026 tax-inclusive estimates for 40 tsubo in suburban Kantō. The two-story surcharge assumes 166 m² of wall after deducting openings.
CladdingInstalled cost (¥/m²)Premium over standard siding (¥/m²)Two-story surcharge (¥ million)
Standard siding12,00000.0
Troweled or sprayed finish18,0006,0001.0
Tile23,00011,0001.8
Premium ceramic panels or tile28,00016,0002.7
ALC exterior wall22,00010,0001.7

For a troweled or sprayed finish similar to Sumitomo Forestry’s, I allowed ¥9,000/m² for the substrate and its installation, ¥2,000/m² for reinforcing and finishing edges, ¥2,500/m² for the finish material and ¥4,500/m² to apply it. The resulting ¥18,000/m² is ¥6,000/m² above standard siding. That adds about ¥1 million over 166 m² or ¥1.2 million over 203 m². I varied the premium from ¥3,000 to ¥10,000/m² to allow for different substrates, finishes and working conditions. The allowance buys a similar texture using materials available to a local builder.

Heating, interior finishes and design time

To approximate Ichijo’s two-story house I started with grade 6 wood, then added ¥4 million for grade 7 insulation and about ¥1.8 million for tile cladding. Floor heating adds ¥3.8 million, made up of panels over 90 m² at ¥30,000/m² and ¥1.1 million for the heat source and controls. A third story adds ¥0.3 million for piping and related work. Interior finishes and fixtures stay at the local builder’s base specification.

For other interiors I multiplied the amount of each finish or fixture by its premium over the base specification. I used one unit price per grade across builders. Two examples show how much of the estimated difference depends on what the owner specifies.

  • For Sumitomo Forestry the ¥3.8 million upgrade covers 85 m² of flooring at an extra ¥10,000/m², 10 doors at ¥60,000 extra each, ¥1 million for kitchen and bathroom fixtures, 8 m of built-in furniture at ¥100,000/m, 20 m² of wood ceiling at ¥20,000/m² and 15 m² of feature walls at ¥10,000/m².
  • For Sekisui House wood the ¥3 million upgrade covers 80 m² of flooring at an extra ¥7,500/m², nine doors at ¥50,000 extra each, ¥0.8 million for kitchen and bathroom fixtures, 6.5 m of built-ins at ¥100,000/m and ¥0.5 million for wall and ceiling finishes.

Both houses also get ¥0.9 million for extra design work on finishes and built-ins. Every house gets ¥0.5 million for extra inspections and records. The cost of design is separate from the cost of the materials. Areas that keep standard finishes are already paid for in the base price.

For Sumitomo Forestry the ¥34 million base, ¥2.8 million for the structure and windows, ¥1 million for exterior walls, ¥3.8 million for the interior and ¥1.4 million for design and inspection give a building subtotal of about ¥43 million. Adding ¥1.35 million for 5 kW of solar, outdoor work, move-in items and fees brings the budget to ¥49.9 million. Raising the interior allowance from ¥3.8 million to ¥7 million takes the total to ¥53.2 million. In the Sekisui House example, increasing the interior allowance from ¥3 million to ¥5.5 million takes the total from ¥47.0 million to ¥49.5 million.

Solar, storage and other allowances

For a specialist installer I allowed a fixed ¥250,000 plus ¥220,000 per kW for solar and ¥1.6 million for a battery of about 7 kWh or ¥2.1 million for about 13 kWh. I deducted ¥250,000 of shared installation costs when panels and a battery went in together. These are installed prices including tax. An alternative calculation uses ¥320,000/kW for solar, based on published averages[33, 28]. Roof-integrated and roof-mounted panels can require different components and waterproofing. Actual capacity depends on panel dimensions, roof shape and clearances.

Outdoor work is ¥2.5 million. Move-in items total ¥1.2 million, or ¥0.9 million where Sekisui Heim’s built-in first-floor air conditioning already covers part of the house. “Included” in the table means the base price covers the finish. Individual air conditioners remain in the move-in allowance even where there is no dedicated heating or cooling upgrade. The outdoor work, move-in items and fees column includes rounding adjustments.

I show a separate ¥1 million reserve for future inspections and similar needs over roughly 30 years. It sits outside both the upfront budget and the loan. The reserve does not price a major builder’s warranty or forecast lifetime repair bills, and it includes no adjustment for inflation or discounting.

Table 12. Local builder’s itemized budget (estimate A)2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo. The inspection reserve is outside the upfront total.
Design to approximateBase house, site work and designThird storyStructure, insulation and windowsCladding upgradeInterior and fixture upgradesFloor heating or dedicated air conditioningAdditional design and inspectionSolar and battery equipmentOutdoor work, move-in items and feesUpfront total (A)Separate inspection reserve
Sekisui House, wood, 2 stories30.5(0.763 per tsubo)0.02.82.73.0None1.41.15.547.0(1.175 per tsubo)1.0
Sekisui House, wood, 3 stories30.5(0.763 per tsubo)3.53.13.33.0None1.40.85.651.2(1.279 per tsubo)1.0
Sumitomo Forestry, wood, 2 stories34.0(0.850 per tsubo)0.02.81.03.8None1.41.45.549.9(1.248 per tsubo)1.0
Sumitomo Forestry, wood, 3 stories34.0(0.850 per tsubo)3.53.11.23.8None1.41.05.653.6(1.340 per tsubo)1.0
Sekisui Heim, wood, 2 stories34.0(0.850 per tsubo)0.00.01.8IncludedNone0.53.65.545.4(1.136 per tsubo)1.0
Ichijo, wood, 2 stories34.0(0.850 per tsubo)0.04.01.8Included3.80.54.65.754.4(1.359 per tsubo)1.0
Ichijo, wood, 3 stories34.0(0.850 per tsubo)3.54.02.2Included4.10.53.65.757.6(1.441 per tsubo)1.0
Aqura Home, wood, 2 stories34.0(0.850 per tsubo)0.01.8IncludedIncludedNone0.50.05.441.7(1.042 per tsubo)1.0
Aqura Home, wood, 3 stories34.0(0.850 per tsubo)3.51.9IncludedIncludedNone0.50.05.545.4(1.134 per tsubo)1.0
Tama Home, wood, 2 stories30.5(0.763 per tsubo)0.00.0IncludedIncludedNone0.50.05.336.3(0.907 per tsubo)1.0
Tama Home, wood, 3 stories30.5(0.763 per tsubo)3.50.0IncludedIncludedNone0.50.05.439.9(0.996 per tsubo)1.0
Sekisui House, steel, 2 stories50.0(1.250 per tsubo)0.00.02.72.5None1.41.55.863.9(1.598 per tsubo)1.0
Sekisui House, steel, 3 stories50.0(1.250 per tsubo)4.00.03.32.5None1.41.15.968.2(1.706 per tsubo)1.0
Hebel Haus, steel, 2 stories50.0(1.250 per tsubo)0.01.51.71.5None0.51.45.762.3(1.558 per tsubo)1.0
Hebel Haus, steel, 3 stories50.0(1.250 per tsubo)4.01.52.01.5None0.51.05.966.4(1.661 per tsubo)1.0
Sekisui Heim, steel, 2 stories50.0(1.250 per tsubo)0.01.51.8Included1.20.53.65.664.2(1.606 per tsubo)1.0
Sekisui Heim, steel, 3 stories50.0(1.250 per tsubo)4.01.52.2Included1.20.53.15.768.2(1.705 per tsubo)1.0

I combined the low assumptions for the base house, quantities, unit prices and services to get the low budget, and the high assumptions to get the high budget. The grade 6 wood base alone ranges from ¥30 million to ¥40 million, and the grade 5 steel base from ¥42 million to ¥60 million. These are scenarios. The unit prices, quantities and sources and house-by-house breakdowns give the inputs.

  1. [29] Fukuda Long Life Design, "グレードと標準仕様 [Grades and standard specifications]," 2026.
  2. [30] Sumairu, "標準工学仕様スペック詳細 [Details of standard engineering specifications]," 2026.
  3. [31] Tsutomu Kaneko Architects, "費用について [About costs]," 2024.
  4. [32] Ikka Architects, "費用について [About costs]," 2025.
  5. [33] Japan Photovoltaic Energy Association, "住宅用太陽光発電システムの費用 [Costs of residential solar power systems]," 2026. Installed cost of solar systems for new homes.
  6. [28] Mitsubishi Research Institute, "2024年度 定置用蓄電システム普及拡大検討会の結果とりまとめ [FY2024 report of the study group on expanding the use of stationary battery systems]," Ministry of Economy, Trade and Industry, 2025. Equipment and installation costs for residential battery systems.
For the second estimate (B), I started at the other end, with the major builder’s price. I replaced its assumed overhead, profit and savings on materials and labor with the costs a local firm would face, then priced equipment and fees on the same basis as in A. For the wood-frame Sekisui House, B gives ¥61.5 million. Both methods put the local price below ¥63.4 million, but they disagree by ¥14.5 million about how much a local builder would charge.

Working backward from a major builder’s price

I took sales costs, model homes, administration and profit out of the major builder’s building subtotal. I added back the estimated savings on bulk purchasing and factory production that the local builder would forgo. I then included local overhead and profit, solar and battery costs, outdoor work and other common costs, and recalculated loan fees. The component mix comes from A. The margins and savings rates are assumptions.

For a salesperson at a major builder I assumed ¥10 million a year including benefits, spread over four houses, or ¥2.5 million per house. For a local builder I used ¥8 million over eight houses, or ¥1 million each. A ¥100 million model home depreciated over ten years, plus ¥12 million a year for rent and upkeep, costs ¥1.1 million per house at 20 sales a year. I allowed ¥0.2 million per house for a local builder’s display space. All of these overhead figures are before tax.

For each major-builder sale, I allowed ¥0.7 million for advertising, ¥1.3 million for administration, ¥0.4 million for research and training, and ¥0.5 million for handling inspection requests. For local sales the respective allowances were ¥0.3 million, ¥0.9 million, ¥0.1 million and ¥0.3 million. I assumed operating margins of 8% for a major builder and 5% for a local firm, measured against the pre-tax selling price of the building subtotal. Since A already includes additional design and inspection, I allowed zero further hours in B and also tested a case with an extra 200 hours for every builder.

On materials and equipment before overhead and profit, I assumed procurement discounts of 12% for general components, 18% for finish products, 30% for packaged floor heating or dedicated air conditioning, and 25% for industrially produced steel components. For labor and fabrication I assumed savings of 10% for conventional wood, 20% for factory-built wood units and 35% for industrial steel. Against these I charged factory and logistics costs of ¥0.4 million, ¥0.8 million and ¥1 million respectively. Solar and battery package prices enter separately.

Table 13. Two estimates for a local builder and their mean2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo. Three-story budgets use assumed premiums. Positive differences mean the major builder costs more.
Design to approximateA, from specificationsB, from the major builder’s priceLocal mean of A and BMajor builder minus local mean
Sekisui House, wood, 2 stories47.0(1.175 per tsubo)61.5(1.538 per tsubo)54.3(1.357 per tsubo)+9.1(+0.227 per tsubo)
Sekisui House, wood, 3 stories51.2(1.279 per tsubo)67.2(1.680 per tsubo)59.2(1.479 per tsubo)+9.2(+0.231 per tsubo)
Sumitomo Forestry, wood, 2 stories49.9(1.248 per tsubo)58.4(1.459 per tsubo)54.1(1.354 per tsubo)+6.2(+0.156 per tsubo)
Sumitomo Forestry, wood, 3 stories53.6(1.340 per tsubo)66.1(1.653 per tsubo)59.9(1.497 per tsubo)+7.6(+0.190 per tsubo)
Sekisui Heim, wood, 2 stories45.4(1.136 per tsubo)47.1(1.177 per tsubo)46.3(1.157 per tsubo)+3.3(+0.082 per tsubo)
Ichijo, wood, 2 stories54.4(1.359 per tsubo)45.7(1.141 per tsubo)50.0(1.250 per tsubo)−3.6(−0.090 per tsubo)
Ichijo, wood, 3 stories57.6(1.441 per tsubo)51.8(1.294 per tsubo)54.7(1.368 per tsubo)−2.4(−0.060 per tsubo)
Aqura Home, wood, 2 stories41.7(1.042 per tsubo)38.2(0.956 per tsubo)40.0(0.999 per tsubo)+1.4(+0.035 per tsubo)
Aqura Home, wood, 3 stories45.4(1.134 per tsubo)44.7(1.117 per tsubo)45.0(1.126 per tsubo)+2.4(+0.060 per tsubo)
Tama Home, wood, 2 stories36.3(0.907 per tsubo)30.6(0.765 per tsubo)33.4(0.836 per tsubo)+0.8(+0.020 per tsubo)
Tama Home, wood, 3 stories39.9(0.996 per tsubo)36.5(0.912 per tsubo)38.2(0.954 per tsubo)+1.6(+0.039 per tsubo)
Sekisui House, steel, 2 stories63.9(1.598 per tsubo)70.5(1.763 per tsubo)67.2(1.680 per tsubo)−3.8(−0.094 per tsubo)
Sekisui House, steel, 3 stories68.2(1.706 per tsubo)79.8(1.995 per tsubo)74.0(1.851 per tsubo)−3.5(−0.088 per tsubo)
Hebel Haus, steel, 2 stories62.3(1.558 per tsubo)68.0(1.700 per tsubo)65.2(1.629 per tsubo)−3.8(−0.094 per tsubo)
Hebel Haus, steel, 3 stories66.4(1.661 per tsubo)75.6(1.891 per tsubo)71.0(1.776 per tsubo)−3.9(−0.097 per tsubo)
Sekisui Heim, steel, 2 stories64.2(1.606 per tsubo)54.5(1.362 per tsubo)59.4(1.484 per tsubo)−8.1(−0.201 per tsubo)
Sekisui Heim, steel, 3 stories68.2(1.705 per tsubo)63.6(1.591 per tsubo)65.9(1.648 per tsubo)−7.8(−0.194 per tsubo)

To get a comparison figure I gave A and B equal weight and averaged them before rounding. The methods share component assumptions, so their errors can carry through to the mean. For the ranges, I varied base prices and unit costs in A. In B, I varied overhead and factory costs from 75% to 125% of their central values, procurement and labor savings rates from 50% to 150%, and each profit margin by ±2 percentage points. The ranges in Section 3.2 cover the lowest and highest values from either method. The two-method calculations (JSON) give the bounds for each.

How much of the price gap do those assumptions explain?

A different use of the same inputs is to hold A’s local selling price fixed and ask how much of the gap with the major builder each expense accounts for. B recalculates the local selling price, so the remainder here answers a different question from the difference between A and B.

Table 14. Breakdown of the gap between the major builder and estimate A2026 two-story budgets for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Positive amounts raise the major builder’s price relative to the local builder’s. The remainder includes rounding.
Builder and frameMajor builder minus local estimate (A)Sales, model homes and advertisingAdministration, development and inspectionsProfitExtra design and managementProcurement and productionSolar, storage and feesUnexplained remainder
Sekisui House, wood16.43.11.02.50.0−3.10.712.2
Sumitomo Forestry, wood10.53.11.02.10.0−3.30.57.1
Sekisui Heim, wood4.13.11.01.40.0−3.10.41.3
Ichijo, wood−8.03.11.00.80.0−3.8−1.8−7.3
Aqura Home, wood−0.33.11.01.10.0−2.50.0−3.0
Tama Home, wood−2.03.11.00.80.0−2.10.0−4.8
Sekisui House, steel−0.53.11.01.70.0−10.90.14.5
Hebel Haus, steel−0.93.11.01.60.0−10.80.24.0
Sekisui Heim, steel−12.93.11.00.60.0−10.80.1−6.9

For Sumitomo Forestry, the major builder’s price exceeds A by ¥10.5 million. The assumed differences add ¥3.1 million for selling, model homes and advertising, ¥1 million for administration, development and inspections, and ¥2.1 million for profit. Procurement and production subtract ¥3.3 million. Solar, storage and financing add about ¥0.5 million. That accounts for about ¥3.4 million of the gap and leaves ¥7.1 million unexplained.

Assigning that entire remainder to profit would raise the assumed operating margin from 8% to about 21%. For context, Sumitomo Forestry reported a gross margin of 24.4% for its non-consolidated housing business in 2025 and 23.2% in the first half of 2026[26]. Operating profit deducts selling and other operating expenses from gross profit. Treating the whole remainder as profit would put the estimated operating margin for this house close to the published gross margin for the broader business. The finishes, services, workload per employee, procurement terms and underlying price estimate all bear on that remainder.

  1. [26] Sumitomo Forestry, "2026年12月期第2四半期 Financial Factbook [Financial Factbook for the second quarter of the fiscal year ending December 2026]," 2026. Gross margins for the entire non-consolidated housing business, which includes more than custom detached houses.
For each house I use the average of the two estimates as a guide. For the wood-frame Sekisui House example, that puts the local budget at ¥54.3 million, about ¥9.1 million below Sekisui House. Both methods use the same assumptions about the mix of materials, so an error there can affect both estimates. I also checked whether they agree on which builder would cost less.

3.2. When the local builder costs less

For two-story wood-frame houses, Sekisui House comes out ¥9.1 million above the local estimate, Sumitomo Forestry ¥6.2 million above and Sekisui Heim ¥3.3 million above. The local estimate is lower in each of these cases under either method’s central assumptions.
For the other three wood-frame designs, Ichijo, Aqura Home and Tama Home all come in lower when I price the local builder’s work item by item. The local builder comes in lower when I work backward from the major builder’s price. Against the mean of the two local estimates, Ichijo is ¥3.6 million cheaper, while Aqura Home is ¥1.4 million more expensive and Tama Home ¥0.8 million more expensive.
For two-story wood-frame houses, the mean local budget is lower by ¥9.1 million for Sekisui House, ¥6.2 million for Sumitomo Forestry, ¥3.3 million for Sekisui Heim, ¥1.4 million for Aqura Home and ¥0.8 million for Tama Home. Ichijo costs ¥3.6 million less than the mean local estimate.
Figure 5: Major and local builders’ budgets for wood-frame houses Upfront budgets for two stories and 40 tsubo in suburban Kantō in 2026, including tax and excluding land. Blue marks the major builder and orange the mean of the two local estimates for a similar specification. The scales give millions of yen per house (bottom) and per tsubo (top). The separate reserve for future inspections is excluded.
A positive difference means the major builder costs more. Percentages use the major builder’s budget as the denominator. The endpoints are the lowest and highest local budgets obtained by varying the inputs to A and B.
Table 15. Major and local builder budgets for two-story wood-frame houses2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo. Local figures average A and B. The percentage difference is relative to the major builder’s budget.
BuilderMajor builderLocal builder (mean)Major builder minus local meanGap as % of major builder’s budgetLocal range across both methods
Sekisui House63.4(1.584 per tsubo)54.3(1.357 per tsubo)+9.1(+0.227 per tsubo)+14.3%38.5–70.6(0.962–1.765 per tsubo)
Sumitomo Forestry60.4(1.510 per tsubo)54.1(1.354 per tsubo)+6.2(+0.156 per tsubo)+10.3%41.2–67.0(1.030–1.676 per tsubo)
Sekisui Heim49.6(1.239 per tsubo)46.3(1.157 per tsubo)+3.3(+0.082 per tsubo)+6.6%39.3–56.2(0.983–1.404 per tsubo)
Ichijo46.4(1.160 per tsubo)50.0(1.250 per tsubo)−3.6(−0.090 per tsubo)−7.8%39.2–69.3(0.981–1.731 per tsubo)
Aqura Home41.4(1.035 per tsubo)40.0(0.999 per tsubo)+1.4(+0.035 per tsubo)+3.4%32.4–51.4(0.809–1.285 per tsubo)
Tama Home34.2(0.856 per tsubo)33.4(0.836 per tsubo)+0.8(+0.020 per tsubo)+2.3%25.4–43.5(0.635–1.087 per tsubo)
Steel gives a different result. For each of the three two-story designs, the major builder’s factory-built steel house comes in below both central estimates for a local builder’s custom steel house. Relative to the mean local estimate, the gap is about ¥3.8 million for both Sekisui House and Hebel Haus, and ¥8.1 million for Sekisui Heim. For Sekisui House, though, the itemized local estimate exceeds the major builder’s price by only about ¥0.5 million. A change of less than 1% in the assumed ¥50 million local base price would erase that gap.
For two stories in steel, all three major builders cost less than the mean local estimate. Sekisui House is about ¥63.5 million versus ¥67.2 million locally, Hebel Haus ¥61.4 million versus ¥65.2 million, and Sekisui Heim ¥51.3 million versus ¥59.4 million.
Figure 6: Major and local builders’ budgets for steel-frame houses Upfront budgets for two stories and 40 tsubo in suburban Kantō in 2026, including tax and excluding land. Blue marks the industrially built house and orange the two-method mean for a comparable custom steel frame from a local builder. Both axes give millions of yen, per house below and per tsubo above. The separate reserve for future inspections is excluded.
A negative difference means the major builder costs less. Percentages use the major builder’s budget as the denominator. The local range combines the minimum and maximum from the two methods as the assumptions vary. All differences use the unrounded budgets.
Table 16. Major and local builder budgets for two-story steel houses2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Parentheses give millions of yen per tsubo. Local figures average A and B. The percentage difference is relative to the major builder’s budget.
BuilderMajor builderLocal builder (mean)Major builder minus local meanGap as % of major builder’s budgetLocal range across both methods
Sekisui House63.5(1.586 per tsubo)67.2(1.680 per tsubo)−3.8(−0.094 per tsubo)−5.9%52.3–89.7(1.307–2.242 per tsubo)
Hebel Haus61.4(1.535 per tsubo)65.2(1.629 per tsubo)−3.8(−0.094 per tsubo)−6.1%51.2–86.9(1.280–2.173 per tsubo)
Sekisui Heim51.3(1.282 per tsubo)59.4(1.484 per tsubo)−8.1(−0.201 per tsubo)−15.7%43.4–80.9(1.085–2.022 per tsubo)
Adding a third story changes the result for Sekisui House and Hebel Haus. With the extra structural and site work I assumed, the itemized estimate puts the local steel-frame house below the major builder’s budget. Working backward from the major builder’s price puts the local house above it.

3.3. Which price differences can the specifications explain?

Consider two of the major builders, Aqura Home and Tama Home. Their two-story budgets differ by ¥7.2 million. At local rates, the higher insulation grade and larger window openings in the Aqura design account for about ¥5.4 million of that gap, including the change in loan costs. Asking builders to price the specification changes separately lets you see how much of the difference buys something you want.

Comparing pairs of houses using estimate A

For two houses with the same frame, I subtracted the difference between the two local estimates from the difference between the major builders’ budgets. A common charge cancels. For instance, raising the local steel base price from ¥50 million to ¥55 million for both Sekisui House and Hebel Haus leaves the difference between their specification costs unchanged.

For Aqura Home versus Tama Home, the local estimate adds ¥3.5 million to go from grade 5 to grade 6 insulation, ¥1.8 million for larger openings and windows, and about ¥0.1 million for the difference in loan costs. The unrounded figures leave ¥1.7 million of the ¥7.2 million builder price gap unexplained.

Sekisui House steel costs about ¥2 million more than Hebel Haus. To approximate its specifications locally, I allowed about ¥1 million more for cladding, ¥1 million more for the interior, ¥0.9 million more for design and ¥0.15 million more for solar and related equipment. Hebel Haus requires an extra ¥1.5 million for insulation. After financing, the difference in local costs is about ¥1.6 million, leaving roughly ¥0.5 million of the builder price gap.

Table 17. Builder price differences after allowing for specification differences2026 two-story budgets for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Subtract the difference in local budgets (A) from the major builders’ price difference to get the remainder. Each column is rounded independently.
Builder pair (first minus second)Major builders’ price differenceDifference at local rates (A)RemainderRange of remainder
Aqura Home − Tama Home (wood)7.25.41.70.3–3.1
Sekisui House − Sumitomo Forestry (wood)3.0−2.95.94.6–7.1
Sekisui House − Hebel Haus (steel)2.01.60.5−0.7 to 1.7
Sekisui House − Sekisui Heim (steel)12.2−0.312.510.3–14.6
Hebel Haus − Sekisui Heim (steel)10.1−1.912.011.0–13.0

For the ranges, I varied the grade 6 premium over grade 5 by ±¥1 million, the unit-price differences for finishes, structure, air conditioning and solar and battery equipment by ±20%, and the additional design fee for finishes by ±50%. I applied the same change to both houses. For Sekisui House steel versus Hebel Haus, the unexplained part varies from −¥0.7 million to +¥1.7 million. Even its sign depends on the specifications.

Compare that with a single major builder against its local equivalent. For Aqura Home, trimming about ¥0.3 million from the ¥34 million local base erases the gap under A. For Sekisui House steel or Hebel Haus, a change of about 0.9% or 1.8%, respectively, in the ¥50 million local base erases a ¥0.5 million or ¥0.9 million gap. Comparing pairs removes costs common to both estimates. Uncertainty specific to each builder’s source price remains.

Among the three steel-frame builders, the assumed finishes, overhead, margins and factory savings still leave roughly ¥11 million unexplained between Sekisui Heim and each of the other two. Raising the assumed savings on labor and fabrication from 35% to 45% for one builder at a time accounted for only another ¥1.5–1.6 million per two-story house. The quotes cover different houses, so the gap tells us little about any one builder’s profit or the savings from its factories. I’d first compare what the three would charge for the same drawings, specifications and services.

Where the two-story steel budgets differ

Sekisui House and Hebel Haus come in ¥12.2 million and ¥10.1 million above Sekisui Heim, respectively. The largest difference is in the building subtotal, for which I used ¥56 million, ¥54 million and ¥42 million. Solar and battery equipment costs ¥2.4 million more in the Sekisui Heim budget, narrowing its lead on the total.

At local unit prices the order changes. Matching Sekisui House costs about ¥0.3 million less than matching Sekisui Heim, and matching Hebel Haus costs about ¥1.9 million less. Sekisui Heim’s dedicated air conditioning (¥1.2 million) and solar and battery equipment outweigh the other houses’ allowances for interiors and design. The ¥50 million steel base is common to all three and cancels in each comparison.

Table 18. Itemized differences between local estimates for steel houses2026 two-story budgets for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Each column subtracts the second design from the first, at the same local rates. Common costs include the ¥0.3 million cooling deduction for Sekisui Heim.
Cost itemSekisui House − Hebel HausSekisui House − Sekisui HeimHebel Haus − Sekisui Heim
Structure and insulation−1.5−1.50.0
Cladding1.00.8−0.2
Interior finishes and fixtures1.02.51.5
Dedicated air conditioning0.0−1.2−1.2
Additional design and inspection0.90.90.0
Solar and battery equipment0.2−2.1−2.3
Common costs, loan costs, and rounding0.00.30.3
Total difference at local rates1.6−0.3−1.9

I then applied the same sales and model-home overhead per house and the same rates for profit, procurement discounts by component, and labor and fabrication savings. Fixed overhead cancels. Profit in yen still varies with the selling price, and savings in yen vary with the mix of components and labor. For two stories, the unexplained amounts are ¥11.6 million against Sekisui House and ¥10.9 million against Hebel Haus.

Table 19. Steel builders’ price differences after allowing for specifications and business costs2026 estimates for 40 tsubo in suburban Kantō. Amounts in millions of yen, including tax and excluding land. Each price difference is the sum of the amounts to its right. The overhead and profit column is net of the local builder’s share. The solar and fee adjustment excludes sums already counted at local rates. The remainder includes rounding. Three-story premiums are assumed.
Builder pair (first minus second)Major builders’ price differenceDifference at local rates (A)Net overhead and profitProcurement and productionAdditional solar, storage and fee differenceUnexplained remainder
Sekisui House − Hebel Haus (2 stories)2.01.60.1−0.2−0.10.6
Sekisui House − Sekisui Heim (2 stories)12.2−0.31.0−0.10.011.6
Hebel Haus − Sekisui Heim (2 stories)10.1−1.91.00.00.110.9
Sekisui House − Hebel Haus (3 stories)3.41.80.2−0.2−0.11.7
Sekisui House − Sekisui Heim (3 stories)12.40.01.0−0.20.111.5
Hebel Haus − Sekisui Heim (3 stories)9.0−1.80.90.00.29.7

Sekisui Heim completes much of each unit in a factory[7]. To test how much that might matter, I raised the assumed labor and fabrication savings rate from 35% to 45% for one builder at a time. With all other inputs fixed, the extra savings were ¥1.5–1.6 million for a two-story house, well short of the remaining gap.

There are also differences in the evidence for each price. I set Sekisui House’s steel building subtotal equal to its wood subtotal because the available sources do not isolate a frame premium. For Hebel Haus I had no direct quote matching the area, story count, tax and site work. For Sekisui Heim I adjusted contracts and original quotes. Changing the shared local steel base leaves these gaps intact. Quotes for the same drawings and scope of work would show whether a gap of that size persists.

  1. [7] Sekisui Chemical, "セキスイハイム(ハウスメーカー)|注文住宅・分譲住宅 [Sekisui Heim (house maker): custom-built and built-for-sale houses]," 2026. Sekisui Heim describes the work it carries out in its factories.

4. What the seven builders offer

If you picked out a house for its view into the garden or its open living room, the frame and window placement may matter as much as the price. I chose Sekisui House and Sumitomo Forestry for their work with space and materials, Hebel Haus for tight urban sites, Sekisui Heim and Ichijo for comfort and energy use, and Aqura Home and Tama Home for different ways of keeping a custom design within budget.
The builders’ photographs illustrate the design details discussed below. The budgets in Section 1 apply to the 40-tsubo examples priced for this comparison.
The photographs are quoted from the builders’ product pages so you can compare the design details discussed in the captions. The corresponding company or rights holder owns each photograph. The page displays a 16:9 crop of each original. The references give the product sources and website terms.
  1. [6] Sekisui House, "戸建住宅・注文住宅 [Detached and custom-built houses]," 2026. Product photography and website terms of use.
  2. [4] Sumitomo Forestry, "木造注文住宅・戸建の住友林業 [Sumitomo Forestry: custom-built wooden and detached houses]," 2026. Product photography and website terms of use.
  3. [5] Asahi Kasei Homes, "注文住宅・戸建住宅 [Custom-built and detached houses]," 2026. Product photography and website terms of use.
  4. [7] Sekisui Chemical, "セキスイハイム(ハウスメーカー)|注文住宅・分譲住宅 [Sekisui Heim (house maker): custom-built and built-for-sale houses]," 2026. Product photography and website terms of use.
  5. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. Product photography and website terms of use.
  6. [8] AQ Group, "AQ Group アキュラホーム [AQ Group Aqura Home]," 2026. Product photography and website terms of use.
  7. [9] Tama Home, "家を建てるならタマホーム株式会社 [Tama Home for building your house]," 2026. Product photography and website terms of use.
Two Japanese housing grades recur in the specifications. Seismic grade runs from 1 to 3 and rates resistance to earthquakes. Insulation grade runs up to 7 and rates how well the walls, roof, floors and windows limit heat transfer. Higher numbers require better performance. At the same insulation grade, air leakage, sun exposure and heating and cooling can still make two houses feel quite different.
Airtightness describes how readily air leaks through gaps in the building. Leaks can create drafts. Window orientation and shading affect how much heat the sun brings in, while ventilation and the way each room is heated or cooled also affect temperatures and bills.

4.1. Sekisui House and custom factory production

A low roof with deep eaves shelters a band of windows. Trees stand just outside the gray, two-story house.
Figure 7: A Shawood house and garden The roofline and the row of windows draw the eye across the facade and into the planting beside it. Photograph © Sekisui House, from the Shawood gallery[6].
Part of the appeal of Sekisui House is the chance to plan the house much as you would with an architect. A designer can lay out the rooms around the way you live, place windows to frame a view of the garden and choose exterior and interior finishes together. Sekisui House makes the components for each design in its factories and coordinates construction and quality checks across its network of builders. That is how it delivers individually designed houses on a large scale[6].
Both its wood-frame Shawood line and its steel frames allow wide windows and rooms with few columns. Shawood offers Bellburn fired ceramic cladding. For one- and two-story steel houses, Dyne Concrete gives the exterior wall a deeply textured surface[6].

4.2. Sumitomo Forestry and wood interiors

Wood flooring and a wood ceiling frame a living room with a sofa, gray walls and wide windows.
Figure 8: Walnut finishes in a MyForest living room MyForest offers interior schemes by species. In this walnut scheme the tones of the doors, ceiling and floor carry through the room to the windows. Photograph © Sumitomo Forestry, from the MyForest gallery[4].
Much of Sumitomo Forestry’s appeal comes from how its designers use the grain and color of wood. They coordinate floors, ceilings and doors and plan the interior around views into the garden. Its Big-Frame (BF) system uses wide columns and rigid joints. That leaves room for large windows and open living areas with few intervening columns[4].
The company standardizes components and specifications to keep construction quality consistent. It offers insulation grade 6 in every region. The choice of wood species, amount of built-in furniture and extent of the interior design work all affect the price[4].

4.3. Hebel Haus and steel frames for urban lots

A white, flat-roofed two-story house with visible panel joints. Vertical louvers screen an outdoor space on the upper floor.
Figure 9: An upstairs outdoor room in a CUBIC house The flat roof and rectangular panels give CUBIC its box shape. Vertical louvers shelter the Sora-no-ma+ outdoor room from neighboring windows while admitting light and air. Photograph © Asahi Kasei Homes, from the CUBIC gallery[5].
Hebel Haus, from Asahi Kasei Homes, combines a steel frame with autoclaved lightweight concrete (ALC) panels in the floors and exterior walls for earthquake and fire resistance. The columns and beams carry the loads. On a small lot, the design can make use of a third story or the roof, or give an upstairs room a sheltered outdoor space like the one in Figure 9[5].
The steel members and their connections vary by product and number of stories. The three-story FREX asgard, for example, uses a heavy steel frame. Insulation grade 6 is standard in energy-efficiency climate zones 5–7, subject to the floor plan[5].

4.4. Sekisui Heim and factory-built modules

A two-story house with a flat roof, off-white tile walls, wide windows and long horizontal balconies.
Figure 10: Balconies on a steel-frame Parfait house The edges of the balconies carry the line of the flat roof across the tiled facade. Photograph © Sekisui Chemical, from the Parfait gallery[7].
Sekisui Heim, part of Sekisui Chemical, builds and inspects room-sized modules indoors and assembles them on site. Finishing most of the house indoors helps keep construction quality consistent when weather or site crews vary. The company plans solar power, battery storage and air conditioning together[7].
Its Parfait line uses steel frames, and The Designer’s Grand To You uses wood. Insulation grade 6 is standard for one- and two-story houses in climate zones 5–7, depending on plan and specification. Module dimensions limit some layouts, and the delivery route has to accommodate the units[7].

4.5. Ichijo and whole-house floor heating

A light-tiled, two-story house with a flat roof and central balcony. Windows of different sizes break up the facade.
Figure 11: Tile and windows on an i-smart house The balcony divides the front into bays. The different window sizes give each bay a different pattern against the pale tile. Photograph © Ichijo, from the i-smart gallery[3].
Ichijo (Ichijo Kōmuten) develops and makes its insulation, windows and other building equipment within the group. Making standardized components in its factories helps it control the cost of supplying well-insulated houses with whole-house floor heating at scale[3].
The i-smart line pairs floor heating with a defined choice of finishes and equipment. Both i-smart and Grand Smart offer insulation grade 7 as standard. Whether a particular house meets it depends on the site, plan and specifications[3].

4.6. Aqura Home and open-plan wood construction

Wood flooring runs from the sofa past the dining table to the kitchen at the back. A tall window faces the seating area, and a railing borders the opening upstairs.
Figure 12: A double-height living room in Chō-kūkan no Ie The living area opens to the floor above. Few columns interrupt the view past the dining table into the kitchen, so the three spaces read as one room. Photograph © AQ Group, from the Chō-kūkan no Ie gallery[8].
Aqura Home, part of AQ Group, breaks down the cost of components and construction tasks to control the price of custom wood-frame houses while maintaining quality. Its proprietary shear walls resist wind and earthquake loads, giving designers room for large windows, tall ceilings and living areas open to the floor above[8].
For new Chō-kūkan no Ie contracts from May 2026, the standard specification is equivalent to insulation grade 6. The site, layout and specifications can affect whether a house achieves that grade. The separate AQ Collection line is grade 5[8].

4.7. Tama Home and the cost of a base specification

A dark gray upper story projects over the entrance of a white house with a single-pitch roof. Vertical louvers cover an upstairs opening.
Figure 13: The projecting upper floor of Dai-Anshin no Ie The change from white cladding to dark gray sets off the upper floor where it overhangs the entrance. The vertical screen breaks up that solid face. Photograph © Tama Home, from the Dai-Anshin no Ie gallery[9].
Tama Home buys equipment in bulk, shortens the supply chain for lumber and has its own branches manage construction. Those choices help reduce material costs and payments to intermediaries on its custom wood-frame houses[9].
For Dai-Anshin no Ie, buyers choose the roof, cladding and equipment from set options. Seismic grade 3 and insulation grade 5 are standard, subject to the plan and specifications. Higher insulation performance and upgraded finishes cost extra[9].

5. Choosing a builder for the house you want

Knowing who will design, build and look after the house can justify paying a major builder more. Sekisui House, for example, trains the people who build its homes and works through group companies and designated contractors[6]. That arrangement matters if you want consistent workmanship on site and a clear point of contact if a defect turns up after you move in.
A local firm can be a good choice if it specializes in the kind of house you want. A portfolio shows what the firm has built. I’d ask which of those houses the designer and site supervisor assigned to my project worked on, and how they would approach my site. I’d ask the same at a major builder.
Suppose Ichijo’s insulation, floor heating and price appeal to you. The living room you want, though, is one you saw at Sumitomo Forestry, with a wood ceiling and a wide window looking onto the garden. Both companies build in wood, and each uses its own frames and components[4, 3]. Before counting on that room at Ichijo’s price, I’d ask its designer how wide the window could be and which finishes they could supply. A local designer might also be able to frame the same view using different materials.
The local budgets in Section 3 assume a firm with the skills and materials for the job. Finding one you trust to build that design at a price you can afford takes time, and that effort matters when you weigh the potential savings. Once you have designs you would be happy to build, ask each team to price the same features and spell out what work and services its quote covers.
  • For large windows, wood ceilings or built-ins, specify window widths, column locations, species and area of wood, and how much custom work you want. Pricing a model-home interior against standard finishes can make the local builder look artificially cheap.
  • For comfort and energy use, ask how the design admits winter sun and shades the windows, whether the builder measures airtightness, and how each room gets ventilation, heating and cooling. Price floor heating or whole-house air conditioning if you want it. If individual units meet your needs, use that basis in both quotes.
  • For a tight site or three stories, check fire requirements, delivery access, and where the frame allows a garage or large windows. Steel and concrete can require different column and wall locations and different access for components. A small lot in Tokyo’s 23 wards needs a quote for that lot.
  • For a fixed budget, agree on the performance, fixtures and finishes that matter. If standard components and a stock plan suit you, have each builder price them and identify what would cost extra. Check the standard specification, work included and after-sales support for the product and contractor.
  • For design and construction, ask the assigned designer for comparable completed houses. Ask who inspects the work, what records you will receive, who corrects defects and whom to call after you move in.
The following groups include the seven builders above and 13 other builders or brands whose published designs address the same needs. I estimated prices only for the original seven. The groups give you a place to start if a particular material, site constraint or feature matters to you.

5.1. Materials and layout

  • Sekisui House plans wide openings in wood and steel and coordinates exterior walls, interior finishes and the garden[6].
  • Sumitomo Forestry uses its BF system for open rooms and matches wood species and tones across interior surfaces[4].
  • Mitsui Home uses lofts and double-height rooms to make use of ceiling height as well as floor area[10].
  • Mitsubishi Estate Home offers fully custom plans for buyers with particular materials or room arrangements in mind[11].
  • Sumitomo Fudosan Housing designs modern exteriors and offers its own kitchens, baths and bathroom vanities[12].

5.2. Insulation and indoor comfort

  • Ichijo combines its insulation and windows with whole-house floor heating[3].
  • Sekisui Heim installs insulation in the factory and offers solar power, storage and air conditioning together[7].
  • Sweden House uses triple-glazed wood-framed windows, calculates insulation performance and measures airtightness[13].
  • Hinokiya designs houses around its Z-Kūchō whole-house air-conditioning system[14].
  • Wellnest Home emphasizes insulation and airtight construction[15].

5.3. Small urban lots and three-story houses

The budgets in Section 1 assume a suburban lot. On a small lot in Tokyo’s 23 wards, I’d ask each builder to price the actual site, taking fire requirements and access for deliveries into account.
  • Hebel Haus uses steel and ALC panels for urban houses that make room for outdoor living on upper floors[5].
  • Panasonic Homes offers layouts for tight urban sites in its three-story Vieuno 3E/S line[16].
  • Daiwa House’s three-story skye3 offers open rooms on constrained sites[17].
  • Taisei Housing’s Palcon concrete houses make use of the height available on small lots[18].
  • Resco House offers concrete-panel construction for small lots and three-story plans[19].

5.4. Standard features and the cost of options

  • At Aqura Home, ask what the wood-frame specification allows for large windows and double-height rooms within your budget[8].
  • At Tama Home, price the base house and the changes you would make to it[9].
  • At Ai Kōmuten, compare the total for the insulation, built-in storage and custom layout you want[20].
  • At Cleverly Home, check how much of the exterior gets tile cladding and what that adds up to for the whole house[21].
  • At Eyeful Home, check which fixtures and finishes come with LODINA’s fixed-price plans and how much you can change the layout[22].

6. Reading a quote

A 2017 price per tsubo is useful if you know what the buyer got for it. Across these two-story houses, budgets rose about 20–60% with each year’s typical equipment. When I priced the upgrades I could identify and held solar and battery capacity at each builder’s 2026 levels, the increases ranged from about 14% to 54%. Ask for separate prices for the features that have changed before using an old quote to set today’s budget.
For two stories, both estimates put a local builder below Sekisui House, Sumitomo Forestry and Sekisui Heim on their wood-frame designs. All three steel-frame builders came in below both local estimates. For Ichijo, Aqura Home and Tama Home the methods give opposite answers. I would use those figures to set a budget, then compare written quotes for the same windows, finishes, equipment and services.
If a particular room drew you to a house, take that example to the designer who would handle your project. Ask how they would build it on your site and who would supervise the work. I’d weigh any savings against the time it takes to find a team I trust with both the design and the construction.

References

  1. [1] "建設工事費デフレーター 時系列(月別) [Construction cost deflator, monthly series through August 2026]," Ministry of Land, Infrastructure, Transport and Tourism, 2026.
  2. [2] Forestry Agency, "令和3年度 森林・林業白書:令和3(2021)年の木材不足・価格高騰への対応 [Annual Report on Forest and Forestry for FY2021: Responses to the lumber shortage and price surge of 2021]," 2022.
  3. [3] Ichijo, "「家は、性能。」こだわりの家づくりなら一条工務店 [“A house is its performance”: Ichijo for carefully built homes]," 2026. See in-house production, i-smart, the grade 7 specifications and the earlier i-series specifications.
  4. [4] Sumitomo Forestry, "木造注文住宅・戸建の住友林業 [Sumitomo Forestry: custom-built wooden and detached houses]," 2026. Sumitomo Forestry describes its custom design work, MyForest, the BF system, quality control and insulation. Its 2024 integrated report discusses material costs and revisions to quoted prices.
  5. [5] Asahi Kasei Homes, "注文住宅・戸建住宅 [Custom-built and detached houses]," 2026. See CUBIC, structural and fire resistance and the FREX asgard announcement and its insulation specifications.
  6. [6] Sekisui House, "戸建住宅・注文住宅 [Detached and custom-built houses]," 2026. Sekisui House describes factory production, its construction teams, Shawood, its wood framing, its two-story steel frames, Bellburn cladding and Dyne Concrete.
  7. [7] Sekisui Chemical, "セキスイハイム(ハウスメーカー)|注文住宅・分譲住宅 [Sekisui Heim (house maker): custom-built and built-for-sale houses]," 2026. See Parfait, factory production, the wood-frame Grand To You and the announcement on grade 6 insulation.
  8. [8] AQ Group, "AQ Group アキュラホーム [AQ Group Aqura Home]," 2026. See component and construction costs, Chō-kūkan no Ie and the grade 6 specification and exceptions.
  9. [9] Tama Home, "家を建てるならタマホーム株式会社 [Tama Home for building your house]," 2026. See purchasing and construction, Dai-Anshin no Ie and the FAQ on seismic and insulation grades.
  10. [10] Mitsui Home, "面積だけでは、家の広さは、わからない。 [Floor area alone does not tell you how spacious a house is]," 2026.
  11. [11] Mitsubishi Estate Home, "自由自邸 自分らしさを自在に。 [Jiyū Jitei: freely your own]," 2026.
  12. [12] Sumitomo Fudosan Housing, "特長 [Features]," 2026.
  13. [13] Sweden House, "高断熱・高気密・計画換気 [High insulation, high airtightness, and planned ventilation]," 2026.
  14. [14] Hinokiya, "全館空調「Z空調」 [Z-Kūchō whole-house air conditioning]," 2026.
  15. [15] WELLNEST HOME, "断熱 [Insulation]," 2026.
  16. [16] Panasonic Homes, "ビューノ3E/S [Vieuno 3E/S]," 2026.
  17. [17] Daiwa House Industry, "skye3(3階建て) [skye3 (three stories)]," 2026.
  18. [18] Taisei Housing, "狭い土地を活かす家 [Houses that make the most of small lots]," 2026.
  19. [19] Resco House, "よくあるご質問・お問い合わせ [Frequently asked questions and inquiries]," 2026.
  20. [20] Ai Kōmuten, "価格・性能・デザイン・保証のバランスを追求した価値ある住まい [A worthwhile home that pursues a balance of price, performance, design, and warranty]," 2026.
  21. [21] Cleverly Home, "クレバリーホームとは? [What is Cleverly Home?]," 2026.
  22. [22] Eyeful Home, "LODINA ロディナ [LODINA]," 2026.